Valve inspection before shipment: the procedure to agree

Guide · ITP · FAT · EN 10204 · MDR

Pre-shipment inspection is a sequence of agreed hold points, not a final visual check. Freeze an inspection and test plan before production, check material certificates by heat number, witness NDE and the shell and seat tests, then release the valves only when the manufacturing data record is complete.

01

The inspection sequence from purchase order to release

  1. 01Freeze the specification and the ITPAgree the inspection and test plan before the purchase order: each characteristic, the reference document, the acceptance criterion, who inspects, and whether the point is hold, witness or review. An ITP written after production starts cannot hold anything.
  2. 02Approve the drawings before machiningApprove the general arrangement drawing, the materials and the pressure class against the datasheet. The approved drawing revision is the reference for every later inspection, and a change after approval needs a new revision rather than a verbal agreement.
  3. 03Check material certificates by heat numberFor each pressure-retaining part, read the EN 10204 3.1 certificate: grade, heat number, chemical and mechanical results, and heat treatment. Match the heat numbers to the parts and to the mill certificates; a certificate for the right grade but the wrong heat is not evidence.
  4. 04Witness NDE and hard-facingRadiography, ultrasonic, magnetic-particle or penetrant testing is performed to the procedure and acceptance criteria in the purchase order. Agree which welds or casting areas are examined, the extent and the operator qualification, then review the reports as records.
  5. 05Run shell and seat tests to the named standardAPI 598 and API 6D define shell and seat tests, with different seat acceptance criteria. Witness the tests, note the gauge calibration certificates, and keep the serial-numbered records rather than a summary line.
  6. 06Witness the factory acceptance testThe FAT covers the pressure tests plus the functional checks: open and close, operating torque where specified, actuator settings and any interlock. Agree in the ITP who attends, which points are hold points, and what evidence is required.
  7. 07Add third-party inspection where the project requires itA third-party inspector witnesses and reports against the agreed ITP; the manufacturer’s own records remain the delivery documents. Agree the body, scope, notice period and who pays before the order, not when the valves are ready.
  8. 08Check packing and marking before dispatchCheck flange faces and weld ends for protection, ports capped, desiccant where specified, and markings against the purchase order and packing list. Photograph the packing and record weights and dimensions before the case is closed.
  9. 09Compile and check the MDR before releaseAssemble the manufacturing data record, index it against the ITP and check every item before shipment. Missing documents are much harder to obtain after the case has left, so a document hold point is worth more than a promise to send them later.
02

The ITP defines what “inspected” means

An inspection and test plan lists, line by line, what is checked, against which drawing or standard, with which method and acceptance criterion, by whom, and at what stage of production. Each line is classed as hold, witness or review: a hold point stops work until it is signed off, a witness point requires notice so the buyer or inspector may attend, and a review point is a document check.

Ask for the ITP with the quotation. A factory that cannot show an ITP before the order is unlikely to follow one after it.

The ITP should name the pressure test standard (API 598 or API 6D), the NDE extent and acceptance criteria, the material certificate type, and every type-test certificate the order requires, such as a fire test, a fugitive-emission test or a cryogenic test.

03

Material certificates: what EN 10204 3.1 proves

EN 10204 defines the types of inspection document. A 3.1 certificate is issued by the manufacturer’s inspection representative who is independent of the manufacturing department; a 3.2 certificate is issued by an independent inspection body. A 3.1 certificate is therefore not third-party inspection.

Check the grade against the specified ASTM or EN designation, the heat number against the part, the chemical composition, the mechanical results and the heat treatment. For duplex stainless steel, add the ferrite content and ASTM A923 results where the specification calls for them. For sour service, the hardness and heat treatment limits come from NACE MR0175 / ISO 15156 and belong in the certificate review.

04

NDE: procedure, extent and acceptance criteria

Non-destructive examination is only meaningful when the purchase order names the method, the extent and the acceptance criteria. “NDE as required” leaves the factory to decide all three. State which welds or casting areas are examined, what percentage, which technique and which acceptance level.

The report should identify the procedure, the operator’s qualification, the equipment, the area examined and the indications found. Review it before the pressure test: a repair after the hydrostatic test means the test has to be repeated.

05

API 598 and API 6D shell and seat tests

API 598 covers inspection and pressure testing for valves generally: shell, backseat and seat tests. API 6D covers pipeline and piping valves and specifies its own shell and seat tests. The two standards have different scopes and different seat-test acceptance criteria, so name the one that governs.

Both use a shell test pressure of 1.5 times the pressure rating at 38 °C. The seat test is where the standards diverge: the permitted leakage and the test duration come from the standard in the purchase order, and a report that quotes the wrong standard cannot be compared with the specification.

For each valve, keep the serial number, test pressure, duration, medium, gauge identification and result. A summary certificate without the test record is not enough to close out a project dossier.

06

What a FAT witness covers

The factory acceptance test is the point where the pressure tests and the functional behaviour of the finished valve are witnessed together: open and close cycles, operating torque where specified, actuator stroke and limit switches, and any interlock or relief feature the datasheet requires.

Witnessing does not replace the records. Agree before the test what the witness will receive: signed test sheets, gauge calibration certificates, photographs and the serial numbers tested. If the buyer cannot attend, the same evidence can be reviewed remotely, but say so in the ITP.

07

Third-party inspection: a scope, not a warranty

A third-party inspector is useful when the project requires an independent signature or when the buyer cannot travel. The inspection body works to the ITP you agreed, not to its own interpretation, so the ITP must be finished before the inspector is booked.

Agree the scope, the notice period, the reports and who pays. The third-party report is evidence of what was witnessed; it does not transfer the manufacturer’s warranty or replace the MDR.

08

Packing and marking before dispatch

Before the case is closed, check that flange faces and weld ends are protected, all ports are capped, desiccant is present where the specification requires it, and the packing suits the transport route and any long storage at site.

Compare the shipping marks, the packing list and the purchase order line by line: tag numbers, size, class, serial numbers and quantity. Record photographs and the case weights and dimensions, because a damage claim is much harder once the container has sailed.

09

What the MDR contains

The manufacturing data record should be indexed and checked against the ITP. For an engineered valve order it normally contains: approved drawings and datasheet; ITP and signed inspection records; EN 10204 3.1 material certificates matched to heat numbers and parts; NDE reports; pressure and seat test records, plus the low-temperature test record where required; type-test certificates such as a fire test to API 607 or ISO 10497 and a fugitive-emission test to ISO 15848-1; certificate of conformity, packing list and certificate of origin; and the installation, operation and maintenance manual.

Hold the document review before shipment. Once the case has left, missing test records can take weeks to recover.

10

Frequently asked questions

What is an ITP in valve manufacturing?
An inspection and test plan is the document that lists what is inspected, against which drawing or standard, with which acceptance criterion and by whom. Each line is a hold point (work stops for sign-off), a witness point (notice given so the buyer or inspector may attend) or a review point (document check).
Is an EN 10204 3.1 certificate third-party inspection?
No. A 3.1 certificate is issued by the manufacturer’s inspection representative, who must be independent of the manufacturing department. A 3.2 certificate is issued by an independent inspection body. Neither is a substitute for witnessing the tests on your order.
Should the pressure test be API 598 or API 6D?
Use the standard your piping class or project specification names. API 6D is written for pipeline and piping valves and specifies its own shell and seat tests; API 598 covers general valve testing. Their seat-test acceptance criteria differ, so do not accept a report that mixes them.
What documents should I receive before shipment?
At minimum: approved drawings and datasheet, the ITP with signed inspection records, EN 10204 3.1 material certificates matched to heat numbers, NDE reports, pressure and seat test records, and the certificate of conformity and packing list. Add low-temperature, fire or fugitive-emission type-test certificates where the contract requires them, and the installation and maintenance manual.
Does an API licence replace third-party inspection?
No. The licence confirms that the facility’s quality system has been audited for the licensed scope. It is not a record of the tests on your valves. Ask for the serial-numbered test records, and add third-party inspection if your project requires an independent witness.
11

Standards cited

  • API Spec 6D: Pipeline and piping valves: design, manufacture, testing and documentation of ball, gate, plug and check valves.
  • API Std 598: Valve inspection and pressure testing (shell, backseat and seat).
  • EN 10204: Types of inspection documents, including the 3.1 and 3.2 certificates.
  • ASTM A923: Test methods for detecting detrimental intermetallic phases in duplex stainless steels.
  • NACE MR0175 / ISO 15156: Metallic materials for use in H2S-containing environments in oil and gas production: material selection, heat treatment and hardness limits for sour service.
  • API Std 607: Fire test for quarter-turn valves with non-metallic seats: a type test of the design.
  • ISO 10497: Fire type-testing requirements for valves: test procedure and acceptance criteria.
  • ISO 15848-1: Fugitive emissions: measurement, test and qualification procedures for valve stem seals, with tightness classes from a type test.
12